This project was based in London at Royal Albert Hall.

H&V were appointed by Royal Albert Hall to carry out the installation of 3No Fan Coil Units above the decorative raft within the Verdi Restaurant. All works were carried out “Out of Hours”.
​​​
The project consisted of the following:
Supply and installation of 3 No. Fan Coil Units (FCU’s) above the decorative raft.
Connection into the existing LTHW and CHW pipework within adjacent plant room.
All associated builders work in connection, including forming opening in the ceiling void and making good.
X
move

This project was based in Crawley at Astral Towers a 8 Floor Office Tower.

Astral Towers houses several companies including British Airways, Tesco, Avios and many others.

The project included the complete removal of the existing AHU, LTHW & CHW pipework, associated ductwork and installation of new flat packed AHU.
X
move

This project was based in London at Poplar Fire Station

We were employed by LFB to reconfigure and fit out a new commercial kitchen/dining area in an operational station. Part of the works included heavy side structural alterations to provide an open plan kitchen/dining area.

A temporary kitchen complete with all services and appliances was installed to the appliance yard whilst works were carried out.
X
move

Centrium 1 is an office block located in St. Albans providing 4 storeys of office accommodation.

We were appointed to carry out the dilapidations to both floors whilst the remaining floors remained occupied. All works were carried out in house and consisted of the following: -

De-Commissioning and remaining redundant air-Handling Plant, ductwork and associated BMS Control Cabling.
Removal and repositioning of FCU units and validation/rebalancing of existing.
General Mechanical adaptions.
X
move

This project was based in London at Croydon Fire Station.

H&V were employed by LFB to reconfigure and fit out wc’s and showers to 3 floors in an operational occupied station/offices.
Part of the works included structural alterations to reconfigure the existing layout.

A temporary wc/shower block complete with all services and a linked covered walkway was installed to the appliance yard whilst the works were carried out.
X
move

This project was based in Guildford at the University of Surrey.

Guildford Court is one of the University’s student accommodation locations spread over 4 blocks. Our works covered all 4 of these blocks.

The project included the complete refurbishment of 112No student bedrooms in 2No blocks, and remedial's to the other 112No student bedrooms in the opposing two blocks. These works worked in conjunction with the replacement of 16 communal kitchens, 48 showrooms / bathrooms, general refurbishments to communal corridors and various external works.
X
move

This project was based in London at The Etons residential flats.

In the summer of 2018, H&V undertook the replacement of 6No CWS storage tanks across 3No 1930's residential blocks.

Eton Rise, Eton Hall and Eton Place each house around 100 flats.

The contract comprised of temporary MCWS supplies to existing GWDS in a phased manor whilst removal of the existing and installation of the new were being carried out.
X
move

2017 PROJECTS

Below are a few projects we carried out in 2017. Please click on the project headings to view the descriptions of works
X
move

This project was based in Kent at Charles Darwin School.

In the summer of 2016, H&V undertook phase 1 of the heating upgrade at Charles Darwin School. Phase 1 comprised of half of the school’s heating being upgraded. This was completed in September 2016 and H&V were asked to carry out the second phase starting in the summer of 2017.

Phase 2 consisted of stripping out and removing the old heating system and replacing with new.
X
move

This project was based in London at BNP Paribas.

BNP Paribas’ head office in Marylebone, consists of 7 floors and is a 24/7 operating building.

This project involved upgrading the supplementary cooling system, comprising of a new chilled water circuit including pumps and ancillaries serving fan coil units located within the ceiling void throughout the first floor, discharging through existing linear slot diffusers. 

X
move


This project was based in London at Leybridge & Newstead Estate.

The project comprised of the phases upgrading of the existing buried cold water mains serving the 4 no. Tower blocks that make up the estate i.e. (Merridale Tower, Block 1 to 44, Block 45 to 88 and Block 89 to 132).
X
move

2016 PROJECTS

Below are a few projects we carried out in 2016. Please click on the project headings to view the descriptions of works
X
move
University of Surrey


Twyford Court is one of the University’s student accommodation locations spread over 9 blocks. Our project covered Blocks A-F.

The project included the complete refurbishment of 195 student bedrooms and ensuites together with the replacement of 24 communal kitchens and general refurbishment to all communal corridors and staircases cores.

X
move


This project was based in London at London School of Economics Rosebery Hall Student Residents.

Rosebery Hall is an occupied premise for higher education with offices and bedrooms being continuously used 24 hours a day within two separate buildings. Rosebery Building and Myddleton Building.

The works consisted of the heating plant room replacements in Myddleton Building and Rosebery Building.
X
move


This project was based in London at The Charter School in Herne Hill.

The Charter School is a senior school housing 1500 students and teachers across 4 separate teaching blocks. It also has a sports block, which is used by both the school and also rented out during evenings, weekends and school holiday periods.

The works consisted of the partial upgrade of the heating plant and replacement of the district heating, hot water and cold-water pipework to the individual teaching blocks.